Skip to content

FDOT A1A Construction Update 5/17/19

IMPORTANT: Safety in the Work Zone

Be alert to all construction equipment when walking, bicycling or driving through the work zone! Remember, safety is everyone's responsibility.

Protecting Turtles

Now that turtle nesting season has started in the Flagler Beach area, local Turtle Patrol volunteers are checking the beach within the project limits every day to locate any new nests. In Segment 3, north of North 18th Street, work cannot begin until the beach is checked. If a nest is discovered, the nest will be marked, and work will not be allowed within 10 feet of the nest, as specified in the environmental permits issued for this project.

The Turtle Patrol also is monitoring the beach in the project limits of Segment 1, from South 25th Street to South 22nd Street, where plans call for dine revetment involving additional sand and plants.

Segment 1 (South 25th Street to South 22nd Street):

Work will be starting on this segment within the next two weeks. This segment involves dune revetment with additional sand and vegetation. Motorist can expect potential short-term lane closures with flagging operations to accommodate the trucks hauling in the new sand and plant material.

Segment 2 (South 22nd Street to South 9th Street):

The contractor continues to work on installing the water main between South 18th Street and South 16th Street. Within the next few weeks, crews will begin installing water main beginning at South 13th Street and working south toward South 16th Street.

The contractor also continues to install French drain system. Over the next few weeks, the contractor will be constructing some sidewalk transitions to side streets on the south end of the segment, and installing curb mats in compliance with requirements of the American with Disabilities Act (ADA).

Segment 3 (North 18th Street to Osprey Drive)

The contractor is expecting to finish drilling the concrete piles for the buried seawall by early July. Work continues on contouring the sand to create the desired dune where wall construction is completed. The first dune plants are expected to be installed within the next few weeks.

Work on this segment also includes the relocation of some utility poles on the north end of the segment. That work has begun and may require short-term lane closures with flagging operations.

Scroll To Top